Week of October 21

Take a look at the most recent progress being made on the King City Library and Senior Centre. Scroll below to see photos!

20191023_114019
The front of the Library and Seniors Centre.
20191023_114110
The East side of the Library, which is the children’s wing.
20191023_114132
The back of the Library and a view of the back entrance.
20191023_114216
The back of the library, the adult wing.

Week of October 14

It now looks like it could maybe be a library! Scroll below to see the latest pictures of the King City Library and Senior Centre.

20191016_150738
The front of the library.
20191016_150846
The East Wing of the library.
20191016_151221
Floor polishing is in progress on the first floor in the community room.
20191016_151240
Drywall stud framing and electrical panel installation work on the lower floor.
20191016_151507
Front view of the senior centre’s side.

Week of October 7

With another week gone by comes another round of photographic evidence of progress being made to the King City Library and Senior Centre. With each week that passes, it seems that the changes become more obvious!

Scroll down to see the latest updates and don’t forget to check back here next week to stay up-to-date!

20191009_123338
The East Wing of the building with the outer glass panel installed, as viewed from the East.
20191009_123403
The North Wing of the building as viewed from the East.
20191009_123427
The East Wing of the building as viewed from the East.
20191009_123458
The North Wing of the building with the outer glass panel installed, as viewed from the North.
20191009_123957
The equipment has been installed in the mechanical room.
20191009_124103
The North Wing of the building as viewed from the West.
20191009_124140
The West Wing of the building with the outer glass panels installed, as viewed from the West.

Week of September 30

Seeing the glass starting to get installed is really making this new King City Library and Senior Centre feel real and we get more excited about it every day!

Are you excited for when the new library and Senior Centre are open?

20191002_125217
The driveway and parking lots asphalt work on the Southside of the property.
20191002_130441
The West Wing of the building with the outer glass panel installed as viewed from the Southwest.
20191002_125422
The East Wing of the building as viewed from the North.
20191002_125443
The North Wing of the building as viewed from the North.
20191002_130353
The West Wing of the building with the outer glass panel installed, as viewed from the West.
20191002_125400
The North Wing of the building as viewed from the East.
20191002_130409
The West Wing of the building with the outer glass panel installed, as viewed from the West.

Week of September 23

This might be the most excited we have been for the weekly pictures! We can now confirm, with certainty, that we will have walls and that they are installed at the new King City Library and Senior Centre.

Not only will we have walls but if you scroll down you will also see that paving has begun for the entryway into the building and preparations have been made to pave our parking lot.

This is an update we have been waiting on for a while, and we are so delighted to see progress happening that we cannot wait to see what next will bring in terms of an update! So be sure to check back regularly to see the construction project as it progresses.

20190925_141557
The West Wing of the building with the outer glass installed as viewed from the South West.
20190925_135658
North of the building as viewed from the East.
20190925_140700
The West Wing of the building with the outer glass installed – as viewed from the West.
20190925_140843
The Drywall stud framing installation work on metal deck.
20190925_141105
Grading of the driveway and parking lot.

September 16

Sometimes with all the changes, it’s nice to just take a moment to appreciate all that has changed. So please scroll below to see what the King City Library and Senior Centre building looks like now.

20190918_131717
The East Wing of the building as viewed from the East.
20190918_131819
The East Wing of the building as viewed from the North.
20190918_131839
The inside view of the East Wing of the basement area with drywall stud framing installation in progress.
20190918_132159
The West Wing of the building as viewed from the North.
20190918_131634
Site view from the SouthEast.

Week of September 9

Not many big changes for the week. Nonetheless, we are happy, as always, to see progress being made!

20190911_130343
The East Wing of the building as viewed from the North.
20190911_130749
Inside view of the East Wing of the basement area with drywall stud framing installation in progress.
20190911_131707
Drywall stud framing installation on the metal deck.

Week of September 3

With all of the changes happening on the site we thought we would share some updated views of the building! Scroll down to take a look at the latest images.

20190904_130218
The North Wing of the building as viewed from the East.
20190904_130215
The North Wing of the building as viewed from the East.
20190904_130340
The North Wing of the building as viewed from the North.
20190904_130637
Inside view of the basement area in the North Wing.

Week of August 26

We never thought we would be so excited to continually see new pictures of freshly poured concrete. And yet we are and we want to share that excitement with you! So scroll down to see the most up-to-date pictures from the King City Library and Senior Centre.

20190828_133314
The view from the South-East.
20190828_133555
Concrete pouring is in progress in the basement.
20190828_133853
The North Wing of the building as viewed from the East.
20190828_134322
Drywall stud framing installation in progress on the metal deck.
20190828_134439
Concrete pouring in the balcony area and formwork of the curb wall the Southside of the building.

Week of August 19

As you will now be able to see, we are planning on having drywall, ductwork and floors in the new building.

20190821_145222
Drywall framing installation at the metal deck.
20190821_145239
A light standard footing at the East side of the building.
20190821_145253
Sprinkler and ductwork in the basement area.
20190821_145314
Slab on grade is 95% poured in the basement area.
20190821_145326
Slab on grade is 95% poured in the basement area.