Week of June 24 & July 1

A lot has happened since we were last able to update the blog! We couldn’t be more excited to find out that we will have a roof and that the fascia is already completed!

Every update we receive means we get more and more excited to be able to move into this gorgeous new space.

20190626_132105
Roofing materials and roofers are onsite.
20190626_132331
The fascia around the building is complete.
20190626_132347
Ductwork, sprinkler system and electrical conduit are progressing well.
20190626_132432
Ductwork, sprinkler system and electrical conduit are progressing well.
20190626_132625
Waste bins have been installed, covers to follow.

Week of June 10

The King City Library and Senior Centre is progressing nicely! Scroll below to see what the latest updates are on the construction site.

20190612_151307
Site grading at the South and East side.
20190612_151335
View from East – North wing of the building.
20190612_153056
Site grading at the South and East side.

Week of June 3

It might be hard to tell, but work is progressing on the site! Our excitement continues to grow as we have been anxiously awaiting to hear about any and all building updates.

We are happy to show you the newest pictures from the job site this week. Please scroll below.

993
View from the South
557
View from west – north wing of the building, site grading work in progress
458
Grading work in progress

Week of May 27

In case you were wondering, the construction on the new King City Library and Senior Centre is still underway. It seems like progress is really moving along now and we cannot wait to see the new pictures next week.

But in the meantime, scroll below to see the latest updates from the building site.

20190529_133339
New sewer and domestic water connection. Backfilling and compaction work underway.
20190529_133007
Structural stud framing support angles installation.
20190529_132811
Duct installation work in progress on the first floor.

Week of May 20

We are so excited to show you the latest updates on the King City Library and Senior Centre build! We know, that ductwork and structural stud framing probably doesn’t excite everyone like it does us.

But if it does, or if you just like looking at the updated pictures, scroll below!

20190522_104207
The ductwork in progress.
20190522_104557
View from the West – North Wing of the building.
20190522_104916
View from the South-West structural stud framing angles works in progress – East wing of the building.

Week of May 13

Every time we turn around there is something new to be excited about at the building site for the King City Library and Senior’s Centre.

Are you excited for the opening of the new library and senior centre? What are you most excited about?

20190515_131853
View from East-North wing of the building.
20190515_132100
View from West – North wing of the building with structural stud framing installed.
20190515_132317
View from South-North wing of the building with electrical rough-in work under progress.
20190515_132941
New domestic water and fire hydrant water connection work under progress.

Week of May 6

It might not seem like much, but there are lots of big changes still happening at the King City Library and Senior’s Centre.

Scroll below to see what the latest is on the job site.

20190510_113115
Site view from South-East structural stud framing installed on the roof.
20190510_113524
View from West structural stud framing on North and West wings of the building.
20190510_114134
New sewer connection work under progress.

Week of April 29

The King City Library and Senior Centre is progressing so nicely! Not only are they working on the frame of the building but they are now starting to work on interior details – like ductwork!

We know that might not seem very exciting to some, but if you are anxiously awaiting this new library like we are then you’ll know what we mean! Having ductwork, floors and the beginnings of electrical wiring is all just more signs of the building to come.

20190501_131634
Ductwork under progress.
20190501_131718
Ductwork under progress.
20190501_132223
Inside view of metal deck on the first floor and electrical rough-in work under progress.
20190501_131815
View from the Northwest wing of the building.

Week of April 22

We are always excited by the progress exhibited at the King City Library and Senior Centre construction site!

Scroll below to see the latest updates and remember to check back regularly to see the progress as it happens.

20190424_110557
Site view from the South.
20190424_105900
Formwork of indoor stairs completed.
20190424_110231
View from North West of the building.